Saturday, October 31, 2009

A Whole 'Nother Level








We got a couple sunny days but have a few steps before we can build the roof.






D K and I installed the collars that support the 2 lofts.  One over the door that's about 3 ft. deep, and the sleeping loft that's 6ft. 8 in.  That leaves about a 6 ft. span between lofts.

 We've put loft floors and some sheathing on.

We have 3 potentially dry days to get the sheathing finished and the housewrap on. But the wheel wells need to be waterproofed from the inside and we may take on that project first thing while we can be open to fresh air since spray foam and adhesive will be used.

A layer of TuTuff vapor barrier between our tiny home and our tarp, along with a temporary ceiling spanning between loft floors has kept it pretty dry.  The water that got in is dried up.   Now we are in the "home stretch" of getting closed up and waterproofed.  We are hoping to move onto flatter ground and start the roof framing in about a week...